In December 2025, PESE – PECC2 Energy Services and Engineering has recently coordinated with relevant parties to successfully complete the energization of the Savan 1 Wind Power Plant in Savannakhet Province, Lao PDR, contributing to the project’s on-schedule achievement of Commercial Operation. PESE acted as the lead entity for the first-time energization of the 220 kV transmission line and the 220 kV substation, ensuring full compliance with safety and technical requirements.

The project, invested by T&T Group, has a total installation capacity of 495 MW and is developed over an area of nearly 9,000 hectares. During the operational phase of the Savan 1 Wind Power Plant, PESE is responsible for:

With proven expertise in O&M and industrial services, PESE continues to reaffirm its capability and commitment to delivering safe, efficient, and sustainable solutions for energy projects.